York Road between Ontario and Stevenson Streets and the entire length of Manitoba Street are to be rebuilt in the summer of 2020
Manitoba Street reconstruction
The City will reconstruct Manitoba Street from Ontario Street to Huron Street. Work includes the installation of sanitary and storm sewer pipes, water pipes, curb, gutter and sidewalks, and final repaving.
Construction starts May 2020
Construction is expected to start in early May 2020 and be completed by September 2020.
Manitoba Street will be closed from Ontario Street to Huron Street in both directions with limited local access. There will be no on-street parking during the project.
Open house notice: Manitoba Street road reconstruction (Wed. Sept. 18)
York Road reconstruction
Construction on York Road from Ontario Street to Stevenson Street includes the installation of sanitary and storm sewer pipes, water pipes, curb, gutter and sidewalks, and final repaving.
Construction starts April 2020
Construction is expected to start in early April 2020 and be completed by October 2020.
York Road will be closed from Ontario Street to Stevenson Street in both directions with limited local access.
Open house notice: York Road reconstruction: Phase 2 (Tues. Sept. 17)
Why come to open houses?
Open houses provide an opportunity to view project information, including maps and schedules, and to ask questions about traffic impacts and access to properties. You’re encouraged to provide comments and feedback to City staff and consultants at the open house.
Most of the planning for these projects has already been completed, but adjustments can still be made, if an important matter has been overlooked, or if there is strong opposition to some aspect of the plan.